送變電工程
Includes electric power transmission and transformation engineering in the electric power system ranging from transmission lines、 substations and supporting facilities and distribution lines
Project
Secondary pressure-reducing reconstructing project of Ji Steel
Constructing company
Shan Steel Group
Equipping plan
110kV AIS transformer station converted to GIS one
Working range
working drawings and completing drawings
Period of project
2011
Project introduction
The project has been put into use since November 2011. The outdoor AIS transformer station of ji Steel was converted to an indoor GIS transformer station with 300-meter cable tunnel at the same time, as a pivotal project of secondary pressure-reducing upgrade and reconstruction and cables buried underground.